Schedule: 2018-2-10

posted in: schedule | 0

20180203_1Last week was one of the coldest days we’ve worked. Siding work on the south side is nearly complete, needing only a few pieces of soffit that were not available last Saturday.

This Saturday:

  • More vinyl siding
  • Continued work on the rough electrical

 

Janice, jangodaire@charter.net,  is now scheduling lunch providers for the coming months. She would be happy to answer any questions about what’s involved with that. Thanks to all who participate in that important part of our day.